Ivesdale moves forward with water project

Ivesdale moves forward with water project

IVESDALE — Village officials are moving forward with plans for a water system project.

The village board voted this week to have engineer Tom Overmyer of Phoenix Consulting Engineers begin design engineering on the water treatment plant and water lines.

Overmyer reported that a Community Development Assistance Program grant application for design engineering had been denied because Ivesdale's median income level was too high. He recommended that the village apply for a public facilities construction grant, which is also administered through the Department of Commerce and Economic Opportunity. That grant would require a 25-percent match from the village.

"Basically if we put a project together and get it submitted, they're going to fund it," Overmyer said. "It's pretty much a slam dunk."

The cost of design engineering for the water plant through February 2014 is estimated at $48,500. Overmyer's services would include preparing a contract and bidding documents and submitting plans and specifications to the Environmental Protection Agency.

Construction would start in 2015.

The total project cost is estimated at $582,000.

 

Comments

News-Gazette.com embraces discussion of both community and world issues. We welcome you to contribute your ideas, opinions and comments, but we ask that you avoid personal attacks, vulgarity and hate speech. We reserve the right to remove any comment at our discretion, and we will block repeat offenders' accounts. To post comments, you must first be a registered user, and your username will appear with any comment you post. Happy posting.