PARIS — Traffic on about a mile of Interstate 74 at Urbana will be reduced to one lane in each direction from September to November, the Illinois Department of Transportation reports.

Weather permitting, work is scheduled to begin Sept. 3 on installation of cable guardrail on I-74 from U.S. 45 to High Cross Road in Champaign County.

The project includes earthwork, adjustments to the existing drainage system and installation of a high tension cable guardrail system in the median.

Traffic on I-74 will be reduced to one lane in each direction at locations where work is ongoing with the left hand lane being closed during daytime hours.

The anticipated completion date is November, weather permitting. The contractor for the $2.1 million work is Cross Construction.

Motorists are advised to slow down and drive carefully through this and all work zones.

Sections (2):News, Local
Topics (1):Road Work

Comments

News-Gazette.com embraces discussion of both community and world issues. We welcome you to contribute your ideas, opinions and comments, but we ask that you avoid personal attacks, vulgarity and hate speech. We reserve the right to remove any comment at our discretion, and we will block repeat offenders' accounts. To post comments, you must first be a registered user, and your username will appear with any comment you post. Happy posting.